CONCRETING OF BOX CULVERT OF DIFFERENT BARANGAYS
Brgy. Tangcaran, Gerona, Tarlac
IJK MAE CONSTRUCTION INC.
Start: March 30, 2022 Target Date: May 28, 2022



CONSTRUCTION OF COVERED COURT AT CARDONA NATIONAL HIGH SCHOOL
DMGR BUILDERS
Brgy. Cardona , Gerona, Tarlac
Start: March 30, 2022 End: April 13, 2022



CONCRETING OF BARANGAY ROAD BRGY. QUEZON, GERONA, TARLAC
Brgy. Quzon, Gerona, Tarlac
DMGR BUILDERS
Start: March 13, 2022 Target Date: April 11, 2022



CONCRETING OF BARANGAY ROAD, BRGY. PADAPADA, GERONA, TARLAC
Brgy. Padapada, Gerona, Tarlac
V. I. T. I. CONST. & SUPPLIES
Start: March 16, 2022 Target Date: April 6, 2022



IMPROVEMENT/REHABILITATION OF MUNICIPAL HALL (ROOFING EXTENSION) MUNICIPALITY OF GERONA, TARLAC
Gerona, Tarlac
DMGR BUILDERS
Start: February 20, 2022 Target Date: June 19, 2022



CONCRETING OF COVERED COURT AT BUENLAG HIGH SCHOOL
IJK MAE CONSTRUCTION
Brgy. Buenlag , Gerona, Tarlac
Start: December 29, 2021 End: February 26, 2022



CONCREATING BARANGAY ROAD (1 & 2)
Brgy. Sulipa, Gerona, Tarlac
IJK MAE CONSTRUCTION INC.
Start: December 1, 2021 January 29, 2022



IMPROVEMENT/REHABILITATION OF ABC HALL MUNICIPALITY OF GERONA, TARLAC
Gerona, Tarlac
DMGR BUILDERS
Start: July 06, 2021 Target Date: January 1, 2022